Mongolian officials open new 17.4 km railway section connecting Shinoortoe and Tolgoit

News Mongolia Editorial team · AI-written, reviewed under our editorial standards · · Reading time 7min read · Views 0 ·
Key — Mongolian officials opened a 17.4 km railway section connecting Shinoortoe and Tolgoit on November 28, 2026.

Mongolian officials opened a 17.4 km railway section connecting Shinoortoe and Tolgoit on November 28, 2026. This section is part of the 127.1 km railway construction between Bagakhangai-Khoshigi Valley and Emeelt. The construction began in August 2026 and took three months to complete.

Construction details and scale

The construction involved 13 national enterprises, over 400 engineers, technicians, and other workers. The new railway is a Class III, 1520 mm gauge, 25-ton axle load line. It has a capacity of 30 million tons of cargo per year.

Construction included 1.07 million cubic meters of earthworks, 179.2 meters of bridges, and five water crossings. The government decided to connect the Bagakhangai-Khoshigi Valley railway to the main railway, as the valley railway was not feasible. The explosion at Djinzhin-Garav was a tragic event that killed people.

Cargo and transport

In 2024, 34 types of dangerous goods weighing about 2.48 million tons were transported into the capital. About 50% of this cargo was diesel fuel, and more than one-third was gasoline. Monthly, 400-500 wagons stopped in Ulaanbaatar and Tolgoit for 5-10 days.

Currently, 6.3 million tons of raw coal are transported by rail within Ulaanbaatar. This coal is used by 41 power plants, including DCS-2, DCS-3, DCS-4, Amgalan, and Nalaykh. The new railway aims to stop dangerous and explosive cargo transport into the city center to ensure public safety.

The Bagakhangai-Khoshigi Valley railway

The 17.4 km railway section opening on November 28, 2026, is reported only by media reports.

Context of the railway project

The construction of the railway section was part of a larger project to connect the Bagakhangai-Khoshigi Valley railway to the main railway. Officials stated that the valley railway was not feasible as originally planned. This decision followed the tragic explosion at Djinzhin-Garav, which killed people.

The new railway is classified as a Class III line with a 1520 mm gauge and a 25-ton axle load. It has an annual cargo capacity of 30 million tons.

The scope of the larger project

The new 17.4 km section is part of a larger 127.1 km railway construction project connecting Bagakhangai-Khoshigi Valley and Emeelt. The work began in August 2026 and required three months to complete. Construction involved 13 national enterprises, 400 engineers, technicians, and other workers.

The project included 1.07 million cubic meters of earthworks, 179.2 meters of bridges, and five water crossings.

Glossary

  • Class III — Class III devices are usually those that support or sustain human life, are of substantial importance in preventing impairment of human health, or present a potential, unreasonable risk of illness or injury and require premarket approval. Examples of Class III devices include implantable pacemakers, pulse generators, HIV diagnostic tests, automated external defibrillators, and endosseous implants.
  • mm gauge — In Poland, the technical condition of the 1,435 mm gauge track is quite good; the 1,520 mm gauge track is slightly worse, but generally good as well. Chełm East functions as a freight and sorting station, and also serves a cement works and a chalk mine (see Chełm Chalk Tunnels). It has 19 tracks of 1435 mm gauge and 5 of 1520 mm gauge.
  • Amgalan — Leaper of Capitalism, a design by Dagdangiin Amgalan depicting a Mongol rider jumping from feudalism to socialism, was reproduced in murals and as a stamp design.

This article was written with AI assistance from multiple news reports and is reviewed by our editors under our editorial principles. Editorial Standards · Tips & Contact

How did you like this post?

Comments 0

Be the first to comment

Contact us

← News Mongolia Home
News Mongolia Get new posts by emailSubscribe to receive new content via email. Unsubscribe anytime.
Was this helpful?Share it with friends & social